A good material takeoff is the foundation of a good quote. This is a straightforward way to do it for railings, gates, frames, stairs and miscellaneous metals.
1. Build a cut list by member
Go through the drawing one member type at a time: posts, top rails, bottom rails, pickets, stringers, braces. Write each as quantity × length, with the size and wall. Add miter angles where they matter, because mitered pieces are measured long point to long point.
2. Nest it into sticks
Suppliers sell tube, angle and bar by the stick (usually 20' or 24'). Run each size through the cut list optimizer with your saw kerf and end trim. The result is the number of sticks to order, which is what you will actually pay for.
3. Price it
If your supplier quotes by the foot or the stick, multiply. If they quote by the pound or hundredweight (CWT), get the weight per foot from the steel weight charts, multiply by the stick length and the number of sticks, then by the price per pound (CWT ÷ 100).
4. Add plate and sheet
For base plates, caps, tabs and gussets, add up the area of each part, add an allowance for the skeleton left after cutting, and price by the sheet or by the pound using the plate weight chart. Outside laser cutting goes in as a vendor cost.
5. Don't forget the rest of COGS
- Hinges, latches, cane bolts, anchors, fasteners
- Paint, primer, powder coat or galvanizing (galvanizers usually price by weight, so you need the total weight)
- Freight, delivery, equipment rental
Then add your markup and labor in the quote builder.
Frequently asked questions
How do I convert a CWT price to price per pound?
Divide by 100. Steel at $95 per CWT is $0.95 per pound.
Should I estimate steel by the foot or by the stick?
By the stick. You pay for whole sticks, so nest the cut list first and price the sticks you will buy.